14.5.11

Kitchen Work Continues

The latest stage of the shop kitchen remodel is the tile backsplash. As I've never done any tiling, Heidi came to do the work while I assisted and learned.

Day One: Laying out the pieces to get an idea of what we might do.
Got two rows applied on the window wall.
Day Two: Finished two rows on the long wall. It was interesting cutting tile to fit around the outlets.
Day Three: Did third (and last) row. Almost finished. Thought we had enough quarter-round to finish the row, but came up short. That means one more day of tiling before we can start grouting.

Next stage, mounting the wall cabinet. The end is in sight!